Once the plan baseline has been approved and the project is underway, project teams deal with change by establishing and using a change control system to receive and review change proposals and accept or reject them after evaluating their impact on project scope, cost and schedule.Select one:A. True B. False

Respuesta :

Answer:

A) True

Explanation:

A project's baseline plan refers to the project's plan starting point. It will serve as the reference point where you can measure the project's progress. Any proposed change to the project must be evaluated using the established change control system. The change control system is not a standard control tool and should be unique to the project based on the project's scope and budget. Changes that negatively affect the project's scope, budget and the schedule should be rejected.