Respuesta :

Answer:

The unit rate = 0.6 holes per hour

Explanation:

Number of holes dug by the team = 12

Total time taken = 20 hours

The unit rate = (Number of holes) / (Time)

The unit rate = 12/20

The unit rate = 0.6 holes per hour