Respuesta :
Answer:
40 Days
Step-by-step explanation:
50 testers
25 test case
-> 10 days
(2 days per 5 cases)
25 testers
50 test cases
2x the effort of 50 testers.
(4 days per 5 cases)
-> 40 days
It will take to complete cases 4 days per 5 cases.
Given that
50 testers can complete 25 test cases in 10 days.
All testers are equally productive.
A project has 25 testers and 50 test cases.
We have to determine
How much time will they take to complete?
According to the question
50 testers can complete 25 test cases in 10 days.
The number of cases completed per day is,
[tex]= \dfrac{50}{25}\\ \\ = 2 [/tex]
The number of cases completed per day is 2.
A project has 25 testers and 50 test cases.
The time will they take to complete is 2x.
= 2(2) = 4 days per 5 cases
Hence, they will take to complete cases 4 days per 5 cases.