Answer:
$66.73
Explanation:
Activity Overhead Cost Activity Base Activity Rate
Engineering and Design $404,712 2,409 $168
Quality Control $269,808 12,848 $21
Machinery $539,616 33,726 $16
Miscellaneous Overhead $134,904 26,400 $5.11
High F
Activity Base-Usage Activity Rate Activity Cost
Engineering and Design 969 $168 $162,792
Quality Control 5,648 $21 $118,608
Machinery 20,286 $16 $324,576
Miscellaneous Overhead 20,286 $5.11 $61,320
Total Overhead cost $667,296
Produced units 10,000
Per unit overhead cost $66.73