Answer:
Explanation:
a. The answer to question (a) goes thus:
Direct materials will be:
= (1,100 × $2.60) × $4.80
= $13,728
Direct labor will be:
= (1,100 × 1/2) × $14.00
= $7,700
Overhead will be:
= $7,700 × 90%
= $7700 × 0.9
= $6,930
b. The standard cost of one unit of product will be calculated as follows:
Direct materials = ($2.60 × $4.80) = $12.48
Add: Direct labor (1/2 × $14.00) = $7.00
Add: Overhead = ($7.00 × 90%) = $6.30
Standard cost = $12.48 + $7.00 + $6.30 = $25.78