The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $3,044. A total of 46 direct labor-hours and 104 machine-hours were worked on the job. The direct labor wage rate is $15 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. The total cost for the job on its job cost sheet would be:__________
a. $11,492
b. $6,722
c. $6,303
d. $9,347

Respuesta :

The correct options are

A)$4,332B)$3,734C)$3,072D)$5,086

Answer:

$5086

Explanation:

Total cost is defined as the amount spent in a production process which involves variable cost such as labour and raw materials which change with volume of production.

In addition fixed cost that remain constant with volume of production are also considered as part of total cost.

In the give scenario

Direct materials is $3,044

Direct labour cost is $15 * 46 = $690

Machine use cost $13 * 104 = $1,352

Total cost = 3,044 + 690 + 1,352 = $5,086