Answer:
the amount that need to be saved each year in order to recover the investment is $858,770
Explanation:
The computation of the amount saved each year is shown below:
= Costing of the new process × (A/P, 15%, 6)
= $3,250,000 × 0.26424
= $858,770
hence, the amount that need to be saved each year in order to recover the investment is $858,770