Answer: c. $1.994
Explanation:
Cost per Equivalent Unit of Production (EUP) for Conversion = Total Conversion costs/ EUP
Total Conversion cost
= Conversion cost for beginning work in process inventory + Conversion cost incurred in the month
= 7,840 + 203,300
= $211,140
EUP = Units completed + Percentage of ending Units completed with regards to conversion
= 92,900 + (90% * 14,450)
= 105,905 units
Cost per Equivalent Unit of Production (EUP) for Conversion = 211,140 / 105,905
= $1.9936
= $1.994