Answer:
The correct option is A
Explanation:
In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!
The option that will be used to compute its earliest finish time is A. the largest EF among the immediate predecessors.
The earliest finish time simply means the possible earliest times when an individual can be able to complete an assigned activity or project.
For an activity with more than one immediate predecessor activity, to compute its earliest finish time will be the largest EF among the immediate predecessors.