Answer:
The NPV is - $14958.49 . The opportunity should not be pursued as the NPV of the project discounted at the interest rate of 15% comes out to be negative . Thus, Nielson Motors should not proceed with the project.
Explanation:
To determine whether the project should be accepted or not, we need to calculate the NPV or Net Present Value of the project. If the NPV is positive, the project should be accepted.
The formula to calculate the NPV is attached.
NPV = - 1000000 + 250000 / (1 + 0.15) + 450000 / (1 + 0.15)² +
650000 / (1 + 0.15)³
NPV = - $14958.49429
The opportunity should not be pursued as the NPV of the project discounted at the interest rate of 15% comes out to be negative. Thus, Nielson Motors should not proceed with the project.