Answer:
Instructions are below.
Explanation:
Giving the following information:
Job 765:
Direct material= $5,670
Direct labor= $3,500
Machine Hours= 27
Job 766:
Direct material= $8,900
Direct labor= $4,775
Machine Hours= 44
Job 765 produced 152 units, and Job 766 consisted of 250 units.
Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour.
Costs sheet:
Job 765:
Direct material= 5,670
Direct labor= 3,500
Allocated overhead= 200*27= 5,400
Total cost= 14,570
Unitary cost= 14,570/152= $95.85
Job 766:
Direct material= 8,900
Direct labor= 4,775
Allocated overhead= 200*44= 8,800
Total cost= 22,475
Unitary cost= 22,475/250= $89.9