Answer:
$2,400 Favorable
Explanation:
Total overhead variance = Actual overhead - Budgeted overhead
Actual overhead $331,500
Budgeted overhead
($55,650×$6) $333,900
Hence:
$331,500-$333,900
=$2,400 Favorable
Therefore the total overhead variance will be $2,400 Favorable