Answer:
cost per units $311.37
Total cost of 21000 units is $6,538,730.00
Explanation:
The total costs next month are analyzed as follows:
unit cost is shown thus:
$
indirect material cost($1,006,000/15000) 67.07
direct labor($2,089,000/15000) 139.27
indirect materials($233,000/15000) 15.53
power(214,000/15000) 14.27
Total variable cost per unit 236.13
total cost= (236.13*21000)+945,000+295,000+148,000+192,000=$ 6,538,730.00
Total costs of 21,000 units= $6,538,730.00