Answer:
The direct materials flexible budget variance for ammonia is $7,000 Unfavorable
Explanation:
In order to calculate the direct materials flexible budget variance for ammonia first we need to Calculate Direct Material Price Variance as follos:
Direct Material Price Variance = Actual Material Purchased(Actual Rate - Standard Rate)
Direct Material Price Variance = 1,400 * ($1.50 - $1.00)
= $700 (Unfavorable)
Therefore, in order to calculate the Direct Material Flexible Budget Variance we would have to use the folloiwng formula:
Direct Material Flexible Budget Variance = Direct Material Price Variance + Direct Material Quantity Variance
Flexible Budget Variance for Ammonia = $700 (U) + $6,300 (U)
= $7,000 (Unfavorable)
The direct materials flexible budget variance for ammonia is $7,000 Unfavorable