Which of the following take place within the Track and Report stage of the resource management process? Select all that apply. Protects the safety and security of personnel and resources Enables resource coordination and movement Estimates date and time of arrival Helps staff prepare to receive and use resources

Respuesta :

Answer:

1) Help staff prepare to receive resources. 2) Protect the safety and security of personnel, equipment, and supplies. 3) Enable resource coordination and movement.

Explanation:

The only alternative that does not apply in this stage is “Estimates date and time of arrival” because the Track and Report Stage focus on creating a clear picture of where the resources and preparing the personnel to use efficiently those resources, ensuring the safety and good use of both human and equipment.