Answer:
Smallest latest start time among its immediate successors.
Explanation:
All activity, (with the exception of the end activity) is expected to have at least one successor. The end activity has zero successors. It is only essential to state the immediate predecessors for the activities to describe the project. An immediate predecessor is the predecessor that is not referred by two or more predecessor relationships.