Answer:
1.6 hour
Explanation:
Given
Rate of Arrival =30 per hour
Rate of Processing = 25 per hour
Open Time = 8am
Close Time = 4pm
How long the last package has to wait before it is processed is calculated by;
Duration = ∆Time/∆Rate
∆Time = 4pm - 8am
∆Time = 8 hours
∆Rate = Rate of Arrival - Rate of Processing
∆Rate = 30 - 25
∆Rate = 5 per hour
Duration = 8 hours ÷ 5 per hour
Duration = 1.6 hours