Job 593 was recently completed. The following data have been recorded on its job cost sheet:


Direct materials $3,190
Direct labor-hours 71 labor-hours
Direct labor wage rate $15 per labor-hour
Machine-hours 175 machine-hours


The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:
a.$6,705
b.$3,219
c.$5,249
d.$4,255