Answer:
b. $34,800; $17,400.
Explanation:
The computation of the allocation cost is shown below:
For type 1:
= 400,000 × $0.12 per bd.ft
= $48,000
For type 2
= 400,000 × $0.06 per bd.ft
= $24,000
For type 2
= 200,000 × $0. p04er bd.ft
= $8,000
The For type 1
= $48,000 ÷ $80,000 × $58,000
= $34,800 would be
= $48,000 +$24,000 + $8,00
= $80,000
Now the allocation cost would be
For type 1
= Type 1 cost ÷ Total cost × shipment cost
= $48,000 ÷ $80,000 × $58,000
= $34,800
For type 2
= Type 2 cost ÷ Total cost × shipment cost
= $24,000 ÷ $80,000 × $58,000
= $17,400