Respuesta :
Identification of LRIP Quantities is required at Milestone B
Option C
Explanation:
Test and Evaluation Master Plan (TEMP) will be used as the planning and management tool for all the test activities starting from Milestone A.
Milestone B is assumed as the official start of a program. Milestone Decision Authority (MDA) ascertains the Low Rate Initial Production (LRIP) quantity at Milestone B.
Milestone B is a MDA led review at final phase of the Technology Maturation and Risk Reduction (TD) Phase in Defense Acquisition Process.
Test Evaluation Master Plan (TEMP) is required as a substitute for the T&E Strategy. Operational assessment (OA) results are required at acquisition stage of Milestone C.
The test and evaluation (T&E) product that is required will be
- C. Identification of LRIP Quantities.
It should be noted that a Test and Evaluation Master Plan is used as the planning and management tool for the test activities.
On the other hand, Milestone B is assumed as the official start of a program. It's a MDA led review at the final phase of the Technology Maturation and Risk Reduction.