Respuesta :
Option B: Remaining duration is the right answer
Explanation:
What are all the possible things which we can do in remaining duration are given below. We need not worry about actual duration or start date. We need to consider the remaining date and give out the best possible.
Call for a meeting and do the following:
Step 1: To identify the pending tasks and the person who is responsible
Step 2: Discuss the reason for delay
Step 3: Explain the current scenario
Step 4: Give tight deadlines and motivate the team to keep up the dates
Step 5: Re-insist on the quality factor
Step 6: Place the responsibility on the team shoulder
Step 7: Ask the team to restart with positive thoughts
Steps to be followed after meeting:
- Follow up about the dates
- Follow up on quality
- Identify the need for hand-holding
- Motivate throughout
The measure of progress that is most important to track the budget here is remaining duration.
What is a remaining duration?
In a project management, it means the period of expected or required time that is required to complete a particular activity.
When we employ the remaining duration, we need not worry about actual duration or start date, all that is consider is the remaining date to give out the best possible.
Therefore, the Option B is correct.
Read more about remaining duration
brainly.com/question/25787382