Answer:
D. A time scaled with owner-furnished items and planned weather losses each month
Explanation:
In a preliminary schedule it is very important to determine the conditions / restrictions that may arise and that will affect the construction. For this, any eventuality in the articles provided by the owner, as well as the losses caused by weather factors, must be incorporated into the construction schedule.