Answer:
(B) Who take the minutes at the next status meeting?
Explanation:
In the project communication matrix which basically considers the channels of communication and establishes the responsibility of different people in the organization, for this the matrix considers answer to all the questions addressing "who" in order to delegate the work, and assigning accountability.
For this there is no such question addressing who will take the minutes to next meeting, as does not involve any major responsibility, and can be taken by any junior staff also.
Therefore, the correct option for the above is
Statement B