Respuesta :
Solution: Estimated time for the work is 40 hour work week.
Estimated payment to 3 laborers working 40 hours at cost $14 per hour is:
[tex]3\times 40\times 14=[/tex] $1680
Estimated payment to 6 masons working 40 hours at cost $24 per hour is:
[tex]6\times 40\times 24=[/tex] $5760
Estimated cost of material = $3143
Contractor wishes to make a profit of $500
Therefore, the mathematical expression that will give the estimated cost of the job is:
[tex]Cost = 1680+5760+3143+500[/tex]
The estimated total cost is:
Cost =$11083
Answer:
The total cost will be $11,083
Step-by-step explanation:
The total time taken to build the wall = 40 hours
There will be 3 labors at $14 per hour totaling to =
[tex]3\times14\times40=1680[/tex] dollars
There will be 6 masons at $24 per hour totaling to =
[tex]6\times24\times40=5760[/tex] dollars
Cost of materials = $3143
Profit amount added = $500
The estimated cost becomes:
[tex]1680+5760+3143+500=11083[/tex] dollars
Hence, the total cost will be = $11,083